Can I Get My Kitchen Renovated Before Christmas?

Short answer

A full kitchen renovation started in November will not usually be finished by Christmas, because it takes 6 to 18 weeks and custom cabinets take weeks to arrive. A kitchen facelift is realistic: painted cabinets, new hardware, a backsplash, lighting and often a new countertop can be done in one to three weeks.

Answered by Robert Milchevich, RM Renovation 2 min read

Key points

  • Full kitchen renovation: 6 to 18 weeks, so plan it for January
  • Kitchen facelift: about 1 to 3 weeks
  • Countertops need templating and fabrication, so book early
  • Order long-lead items before the holiday slowdown
Renovated white kitchen with an island, quartz countertops and pot lights

I get this question every November, usually from someone who is hosting the family dinner this year. My honest answer is that it depends on what "renovated" means to you.

Two options before Christmas: a kitchen facelift in one to three weeks is ready for the holidays, a full kitchen renovation takes 6 to 18 weeks and finishes in the new year

Why a Full Kitchen Renovation Will Not Fit

A full kitchen renovation in Toronto takes 6 to 18 weeks of work, depending on the size and whether walls or plumbing move. Before that, there is design, measuring and ordering. Custom cabinets usually take several weeks to be built, and nothing else can be finished until they are in. If we start a full renovation in November, you would be cooking on a hot plate over the holidays. That is not the experience I want for any client. Our kitchen renovation cost guide explains what drives the timeline and the budget.

What We Can Finish Before Christmas

  • Cabinet painting and new hardware: the biggest change for the money, usually about a week
  • A new backsplash: two or three days of work once the tile arrives
  • Lighting: pot lights, pendants over the island and under-cabinet lights
  • A new countertop: quartz is measured after the old top comes off and then fabricated, so we book this as early as we can
  • A new sink and faucet to go with the new countertop

Together, these can make a kitchen look new in one to three weeks. If you also want new floors in the kitchen, read the best flooring for a kitchen first.

If You Want the Full Renovation, Plan It Now

November and December are the best time to design a kitchen you will build in January. You get the design finished without rushing, your cabinets are ordered before the holiday slowdown, and work starts in the new year when your house is quiet. You will have your new kitchen well before spring. If you are in Mississauga, our renovation contractor page for Mississauga shows the kitchens we have built there, and for Toronto see kitchen renovation in Toronto.

Want to talk it through? See our Google reviews from GTA homeowners and book a free consultation. For other quick projects before the holidays, read holiday-ready home upgrades you can still finish before December.

People also ask

What Temperature Should I Leave My House at When I Am Away in Winter?

I recommend leaving the thermostat no lower than about 15°C while you are away for a few days in winter. The City of Toronto says areas with water pipes should stay above 8°C, and the corners where pipes run are always colder than the thermostat. For a longer trip, ask your insurer what they require; many expect the water shut off and the lines drained if the house will be vacant.

Read the full answer →

How Long Does a Home Addition Take?

A home addition in the GTA usually takes 8 to 14 months from start to finish. That window covers three stages: design, permits, and construction. The build itself runs 3 to 8 months. The rest goes to planning and city approvals.

Read the full answer →

Custom vs Stock Kitchen Cabinets: Which Is Right for Your Kitchen?

Custom cabinets fit your exact space and can last for decades, while stock cabinets cost far less and install quickly. The right choice usually comes down to three things: your budget, your timeline, and how your kitchen is built.

Read the full answer →

Why Ventilation Is Important in Bathroom and Kitchen Renovations

When planning a kitchen or bathroom renovation in Ontario, most homeowners get excited about countertops, tile patterns, and cabinetry. But one essential component often gets missed: ventilation. At RM Renovation in GTA, we’ve renovated hundreds of homes across Ontario, and poor airflow is one of the most common hidden problems we uncover during projects.

Read the full answer →

Planning a renovation?

Tell us about your project and we will get back to you with a free, no-obligation quote.

Get a Free Quote →